| Electrice |
| Electrical cable 3x1.5 mm, 1kv |
| Electrical cable 3x2.5 mm, 1kv |
| Electrical cable 5x4 mm, 1kv |
| Flexibile pipe for protection 25 mm diam |
| Flexibile pipe for protection 20 mm diam |
| Power sockets 220V, 16A, wall mounted Legrand or similar |
| SP&N supply, 32 A, commando outlet |
| Light switch, Legrand Mosaic or similar, 10 A |
| Light fixture 4x18W, matching existing, Philips or similar |
| Downlight 2x26W,opal, Philips or similar |
| Electrical connection boxes 100 x 100 mm |
| Electrical connection boxes 70 mm diam |
| Plastic box to protect the endings of the cables |
| Bachmann PDU (extension leed) equipped with 1 electrical sockets and safety power indicator, cord length 3 metersand 1 data ports |
| Floor box 16 modules equipped with 4 electrical outlets and 8 data RJ45 modules, recessed mounted in concrete,Legrand Mosaic or similar |
| Aluminium column 2.7 m Legrand fully equiped |
| Cable management PVC crossing plinth |
| Circuit brakers 10A/16A/32A |
| Connectors with 5 pins |
| Metallic trays - 100x50 (including montage kit) |
| Metallic trays - 200x50 (including montage kit) |
| Metallic trays - 300x50 (including montage kit) |
| Auxilliary materials (connectors, end dry heads, tape, tags etc) |
| Earth connection to server room |
| Reconfigure existing light fixtures |
| Modify switching and electrical circuits to suit new partitioning |
| Dismantle - reassemble electrical distribution pannels acc. To MEP design |
| Running tests for electrical system |
| Mecanice |
| Cable Csyy-F 9x1mm |
| Insulated flexibile duct Dn 200 |
| Insulated flexibile duct Dn 250 |
| Metallic ducting for inlet/exhaust air, different sections, connection pieces included |
| Inlet grille with ALP plenum, 600 x 600 |
| Outlet grille EggCrate, 600 x 600 |
| Pipework - hot and chilled water supply for fan coil, kitchen sink, waste, gravity condensate connection, sprinklers piping, taps etc |
| Encased sewage pump |
| Rauhis pipe including fittings with 20 x 2,3 mm |
| Ball valve FI-FE, Pn 10, 1/2” |
| Electric water heater 10 l |
| Auxiliary materials |
| Ventilation works acc to the list of materials |
| Modifications to HVAC System to suit new layout |
| Sanitary works |
| Running tests |